Oudtshoorn, 09 March 2021 – The Oudtshoorn Municipal Technical Services has started with upgrading and rehabilitation programme of streets, roads and sidewalks in the Greater Oudtshoorn in the beginning of March. 

The streets and roads upgrading programme started on 2 March 2021 and is envisaged to be completed on 22 March 2021. The rehabilitation of streets and sidewalks comprises patching, kerbing, reseal, micro page overlay, mill & fill of over 30 streets and sidewalks in Oudtshoorn CBD, Oudtshoorn North, parts of Bridgton and Bongolethu.

The following Works are being undertaken in the Oudtshoorn Municipal Area as from 1 to 22 March 2021:

PATCHING & KERBING

  • Bloem Street – Patching
  • Vrede Street – Patching
  • Condor – Splitter Island
  • Rand Street – Patching
  • Jubilee Street – Patching
  • Badenhorst Street – Kerbing
  • Bergin Sidewalk – Kerbing
  • Park Road – Dropped Kerbs
  • J.V.R – Dropped Kerbs
  • Brown Street – Patching
  • Kloof Street – Patching
  • Badenhorst Street – Patching
  • Loop Street – Patching
  • Adderley Street – Patching
  • 12th Ave (Bhongolethu) – Patching
  • Willow Street (Bridgton) – Patching
  • Petunia Street (Toekomsrus) – Patching
  • Zebra Sidewalk – Kerbing
  • Bergin Sidewalk
  • Bergin Sidewalk – Pavement Mix
  • Bergin Sidewalk – Pavement Mix
  • Zebra Sidewalk – Pavement Mix
  • Zebra Sidewalk – Pavement Mix

RESEAL & REHABILITATION

  • Provincial Roads
  • Mill & Fill – 100mm BTB + 40mm W/C
  • Mill & Fill – 40mm Colto Medium
  • Rademeyer Road (Oostelike to Speedhump)
  • Mill & Fill – 40mm Colto Medium Patching – Paver
  • Adderley Street (St. John to St. Saviour)
  • St George’s Street (St Saviour to Loop)
  • Mill & Fill/Key & Overlay – 30mm Colto Fine
  • Adderley Street (St. Johns to St. Saviour) – Keys {Nightwork}
  • Kerk Street (Adderley to Baron Van Rheede)- Mill & Fill 30mm {Nightwork}
  • St. Johns Street (Adderley to Baron Van Rheede) – Mill & Fill 30mm {Nightwork}
  • Olivier Street- Mill & Fill 30mm {Nightwork}
  • Condor Street – Mill & Fill 30mm Colto Fine
  • 2nd Avenue – Mill & Fill 30mm Colto Fine

MICROPAVE OVERLAY

  • Rand Street – Kerk to St. Saviour
  • Jubilee Street – St. Saviour to Kerk
  • Rosspark Crescent- Rand to Rand
  • Brown Street- Van Der Riet to St. Saviour
  • St Georges Street – St. Saviour to Kerk
  • Bad Street – Kerk to Bad 
  • Loop Street – Adderley to Hoog
  • Kloof Street – Adderley to Cul De Sac
  • Adderley Street – Hoop to Victoria
  • Gillis Street – Theron to Cul De Sac
  • Johnson Crescent – Johnson to Cul De Sac
  • Bloem Street- J.V.R to Park
  • Vrede – J.V.R to Park
  • Willow Street – Poplar to Stinkhout
  • 12th Avenue (Bhongolethu) – Circle to 3rd Avenue
  • Petunia Street – Weyers to Brick Paving

Some works will be done at night when the traffic flow on the streets is less or quiet. The Municipal technical services department apologises for any inconvenience caused by the street/road works.